Example: Predicted due date of an epic
Given the Total remaining estimate in an epic, provide a Predicted Due Date.
A valid configuration for this Calculated Date-Time Field:
The display format is configured as shown:
Text to be parsed
addTimeSkippingWeekends({00057}, {10200}*{DAY}, LOCAL, {FRIDAY}, {SATURDAY})
Note that:
- {00057} is the field code for Current date and time
- {10200} is the field code for custom field Epic Remaining (see Total remaining estimate in an epic)
Once configured and added to an issue screen (e.g. an epic), the result will look like this: